top of page
Apartment Building

Publications

Can You Deduct Backcharges Without a Strict BIF Act Payment Schedule?

  • Writer: John Merlo
    John Merlo
  • 11 hours ago
  • 11 min read

KEY TAKEAWAYS

  • Short-paying a civil works invoice based on perceived defects or backcharges, without issuing a valid statutory payment schedule, exposes your business to liability for the full claimed amount.

  • Under Queensland's statutory payment regime, the right to set-off liquidated damages against a subcontractor depends on strict compliance with the response window under section 76 — being the earlier of the contractual period or 15 business days.

  • Contractual clauses designed to override or limit statutory payment rights, including "pay when paid" provisions, are void and unenforceable under section 200 of the Act.

  • Failing to respond correctly to a valid payment claim converts an otherwise disputable invoice into a statutory debt recoverable in a court of competent jurisdiction.





A civil subcontractor submits a $120,000 progress claim for bulk earthworks on your subdivision project. Their compaction failed independent testing last week, and you have already incurred $40,000 in rework costs to keep the civil program on track. Your project manager crosses out the total, writes "defective work – unpaid" across the front of the invoice, and returns it to the subcontractor via email. Ten days later, the subcontractor files for adjudication, and you realise your informal deduction carries no legal weight under Queensland law. The 15-business-day window to issue a valid payment schedule is ticking, and relying on your internal assessment of the defect to withhold payment is about to trigger full statutory liability.

 

 

Responding to the Civil Subcontractor’s Invoice: The 15-Day Decision Point

The clock starts the moment your company receives a subcontractor's invoice, forcing an immediate decision on how to handle defective earthworks or disputed variations. Short-paying the invoice based on your internal assessment is not a viable option; you must deploy specific statutory mechanisms immediately to preserve your right to withhold funds.

 

Statutory Debt Creation vs. Common Law Right of Set-Off for Civil Works

In standard contract law, if a party breaches their obligations, you often have a common law right to set-off your damages against what you owe them. However, in the construction industry, the Building Industry Fairness (Security of Payment) Act 2017 (BIF Act) significantly curtails how and when you can exercise that right. The statutory framework is designed to keep cash flowing down the contracting chain, and it achieves this by requiring you to raise any set-off in a valid payment schedule — failing which you lose the ability to rely on that set-off as a defence to a statutory debt claim or in adjudication proceedings.

 

In practice, deductions cannot be raised as a defence to a statutory debt claim or relied upon in adjudication unless they are detailed in a valid statutory payment schedule issued within time.

 

If you attempt to apply a common law set-off without fulfilling the statutory procedural steps, the legislation treats the full claimed amount as a distinct statutory debt. The Queensland Building and Construction Commission actively oversees the security of payment framework to ensure these strict payment protocols are followed.

 

Navigating Section 76 and the 15-Business-Day Deadline

The legislation does not allow you to hold an invoice indefinitely while you investigate defects. Under section 76 of the BIF Act, a respondent must respond to the payment claim by giving the claimant a payment schedule within 15 business days, unless the relevant subcontract specifies a shorter timeframe.

 

Failing to formally respond within this window — which may be shorter than 15 business days if the construction contract prescribes an earlier deadline — strips the respondent of their right to unilaterally deduct backcharges or liquidated damages for that specific claim. If you miss this deadline, you lose the procedural right to dispute the invoice value at this stage, which frequently escalates into an unmanageable subcontractor dispute.

 

The Christmas Shutdown Trap for Civil Contractors

Civil contractors frequently miscalculate the 15-business-day response window by relying on standard calendar days or industry RDOs rather than the strict statutory definition. The legal calculation of a BIF Act business day explicitly excludes specific holiday periods, creating a well-known administrative hazard.

 

The trap works like this: Schedule 2 of the BIF Act defines "business day" as excluding Saturdays, Sundays, public holidays, and — critically — every day falling within the periods of 22 to 24 December, 27 to 31 December, and 2 to 10 January. That exclusion effectively adds around 20 calendar days to the statutory clock during the holiday period, but only if you are counting correctly. The problem in practice is that many civil contractors' accounts departments count calendar days from the date of receipt, assume the standard industry shutdown covers them, and diarise a response date that is actually weeks too late — or, conversely, panic unnecessarily when there is in fact more time available than they realise.

 

A common scenario: a subcontractor serves a progress claim on 18 December. The project manager glances at it, assumes nothing can happen over the break, and parks it until the site reopens in mid-January. By the time the QS pulls together the defect schedule and someone drafts the payment schedule, it is late January — and depending on how public holidays fall in that particular year, the 15-business-day window may have already closed. The 2023 Queensland Court of Appeal decision in Allencon Pty Ltd v Palmgrove Holdings Pty Ltd [2023] QCA 6 confirms that where a construction contract prescribes a shorter period for delivering a payment schedule than the BIF Act's 15-business-day maximum, the contractual period applies as the earlier deadline under section 76(1)(a), and courts will enforce that shorter deadline strictly.

 

The practical takeaway is blunt: if your business receives any payment claim in the first three weeks of December, treat it as urgent. Do not rely on your standard RDO calendar or your enterprise agreement shutdown dates to calculate the statutory deadline — they have no bearing on the BIF Act calculation. The safest approach is to issue a compliant payment schedule within time, even if it is conservative, and refine your position through further correspondence or adjudication if needed. A compliant payment schedule issued on time is far more valuable than a detailed one served late.

 

 

Why Deducting Liquidated Damages Without a Payment Schedule is Fatal

If you ignore the invoice or send a casual email stating you are withholding funds for defective drainage work, the law considers you to be defaulting on payment for the entire claim. This section outlines exactly how your full liability crystalises into a statutory debt and why your standard contract terms will not save you from BIF Act penalties if you make invalid deductions without a compliant payment schedule.

 

How Section 77 Converts Defective Work Claims into Statutory Debts

Warning: Failing to issue a valid response under section 77 of the BIF Act renders your business statutorily liable for the full amount claimed on the due date. Once that liability crystallises under section 77, section 78 provides the claimant with a mechanism to recover the amount as a debt in a court of competent jurisdiction — meaning a highly disputable invoice can become an enforceable debt, and the actual quality of the subcontractor's work may become irrelevant if the statutory deadline is blown. The severe consequences of a payment schedule failure Queensland mean that obtaining advice from Queensland building and construction lawyers is necessary before withholding funds.

 

The Failure of Contractual Offset and "Pay When Paid" Clauses

Civil contractors often assume that an offset clause or a "pay when paid" provision in their subcontract will justify withholding money. While an offset clause is intended to allow a head contractor to deduct costs for a subcontractor's breach, the enforceability of this clause depends on strict compliance with the BIF Act.

 

Under section 200, the provisions of the Act have effect despite any provision to the contrary in any contract, agreement, or arrangement. This means that any contractual attempt to bypass the payment schedule requirement, or to rely on prohibited "pay when paid" terms under section 74, is of no effect. Seeking early commercial law advice clarifies why relying solely on your contract terms creates a separate exposure channel for statutory liability.

 

Essential Elements of a Valid BIF Act Payment Schedule

To be valid in Queensland, a BIF Act payment schedule must explicitly state the amount the respondent proposes to pay and provide comprehensive reasons for any shortfall. A compliant payment schedule must include the following essential elements:

 

  • Identification of the specific payment claim to which it responds (such as a referenced invoice number or variation claim).

  • A clear statement of the exact amount the respondent proposes to pay (the scheduled amount).

  • Detailed calculations and comprehensive reasons explaining why the scheduled amount is less than the claimed amount.

 

Why Merely Noting "Defective Works" on the Invoice is Insufficient

Writing a vague reason like "withheld for defective earthworks" on a returned invoice fails the statutory test for a payment schedule. The respondent must quantify the exact deduction and link it directly to specific contractual breaches or formal rectification quotes.

 

If you intend to levy liquidated damages for late completion, those calculations must be fully detailed within the document. Failing to provide this technical detail will be relied on as evidence that the payment schedule is invalid, leaving the contractor exposed. Consulting a construction lawyer can ensure your reasons are sufficiently articulated to withstand statutory scrutiny.

 

 

Pursuing the Principal: Recovering Your Own Unpaid Civil Works Invoices

The same statutory framework that protects your subcontractors applies equally against a principal who refuses to pay your civil contracting firm. When the principal ignores your valid progress claim or attempts to ambush you with unsubstantiated backcharges, you have rapid debt recovery options that bypass slow, traditional litigation.

 

Section 78 Debt Recovery Pathways

When a Queensland principal fails to issue a payment schedule, the civil contractor may recover the unpaid invoice as a statutory debt in court under section 78 of the BIF Act.

 

Under section 78, a claimant may bypass standard contractual claims and either pursue the unpaid money as a debt in any court of competent jurisdiction, or alternatively apply for adjudication of the payment claim. The claimant may also give written notice of intention to suspend work under the contract. The statutory debt mechanism is faster than traditional breach of contract litigation, as courts may grant summary judgment based purely on the principal's procedural failure. However, before commencing court proceedings under section 78, the claimant must first issue a warning notice under section 99 of the BIF Act to the respondent.

 

This notice must be in the approved form and given no later than 30 business days after the due date for payment. Critically, if the claimant fails to issue the section 99 notice within this window, the right to recover the amount as a statutory debt in court is lost — even if the respondent's failure to provide a payment schedule is undisputed. While a litigation lawyer can assist with court filing, the appropriate court depends on the quantum of the claim — with the Magistrates Court, District Court, or Supreme Court each having their own jurisdictional limits.

 

The "Request for Particulars" Strategy Against Vague Set-Offs

When a principal withholds payment and files a defence alleging "defective works" without specifying which works, where, when the defects manifested, or what standard was breached, the civil contractor faces what amounts to a fishing expedition funded at the contractor's expense. The Uniform Civil Procedure Rules 1999 (Qld) provide a direct remedy: a formal Request for Particulars demanding that the principal itemise every alleged defect by location, reference the specific contractual or Australian Standard specification said to be breached, quantify the rectification cost for each item, and identify the date each defect was first observed.

 

In practice, this procedural step does three things simultaneously. First, it freezes the principal's ability to broaden or shift their allegations later in the proceeding — once particularised, they are locked in. Second, it frequently exposes that the principal's "defects" list is either recycled from a single site inspection report that does not support the quantum withheld, or consists of maintenance items that fall outside the defects liability period. Third, if the principal fails to respond adequately, the contractor's solicitor can apply to the court for an order compelling particulars, and if the principal still does not comply, a Strike Out Application under the UCPR can eliminate the unparticularised portions of their defence entirely.

 

The real tactical value emerges at the cost level. A vague defects defence, left unchallenged, will force the contractor into expensive discovery, expert reports across multiple disciplines, and protracted interlocutory skirmishes — all before the substantive hearing. By contrast, a well-drafted Request for Particulars served within the first 28 days often reveals that the principal cannot technically substantiate deductions anywhere near the amount withheld. At that point, the matter frequently resolves commercially because the principal's solicitor recognises the strike-out risk and advises settlement rather than incurring the costs of an application they are likely to lose — with an adverse costs order attached.

 

Identifying and Curing "Invoice Formatting Fatalities"

A claimant cannot trigger the powerful section 78 debt recovery pathway if their original payment claim validity is compromised. For example, under the Building Industry Fairness (Security of Payment) and Other Legislation Amendment Act 2020, specific supporting statements are required, and failing to include them can invalidate the claim. Merely writing "Invoice" is insufficient if the document fails to identify the construction work adequately or meet the strict contractual prerequisites required by the BIF Act. If the initial payment claim is deemed invalid, the principal's failure to issue a schedule will not automatically result in a recoverable statutory debt.

 

 

Conclusion

When that $120,000 progress claim for bulk earthworks lands on your desk, your response dictates your financial exposure. Simply crossing out the total and writing "defective work" on an invoice is not a legal defence in Queensland; it is a critical procedural failure. The BIF Act does not wait for you to gather independent testing reports or finalise your internal damage calculations before the statutory clock runs out.

You now understand that the right to set-off backcharges is strictly governed by the statutory deadline for issuing a valid payment schedule — being the earlier of the period prescribed in your construction contract or 15 business days after receiving the claim. Relying on standard contract clauses or "pay when paid" provisions will not protect you from statutory liability if you ignore this deadline. Conversely, you also know that when a principal attempts to use vague defect claims to withhold your money, their failure to provide a compliant schedule opens a direct pathway for you to recover the funds as a statutory debt.

Your immediate next step is to review your internal accounts payable process to ensure that every disputed subcontractor invoice is met with a fully detailed, compliant statutory payment schedule within the applicable deadline under section 76 — and never just an informal email.

 


FAQs

What happens if I just short-pay a civil subcontractor’s invoice without issuing a payment schedule?

Failing to provide a payment schedule within the earlier of the contractual period or 15 business days may make you statutorily liable for the full amount claimed under section 77 of the BIF Act. The subcontractor can often bypass traditional litigation and — after issuing a section 99 warning notice — may secure summary judgment for the unpaid amount as a statutory debt.

Can I rely on the offset clause in my subcontract to withhold payment for defective earthworks?

While an offset clause is designed to let you deduct costs for a subcontractor's breach, the enforceability of this clause depends on strict compliance with the BIF Act. Section 200 invalidates any contractual attempt to bypass the statutory payment protections, meaning you must still issue a valid payment schedule.

What details must be included in a valid BIF Act payment schedule in Queensland?

To be valid in Queensland, a BIF Act payment schedule must explicitly state the amount the respondent proposes to pay and provide comprehensive reasons for any shortfall. Vague statements like "withheld for defective work" are insufficient; you must quantify the exact deduction.

How does the Christmas shutdown affect the 15-business-day timeline for responding to a payment claim?

The statutory definition of a business day under the BIF Act excludes Saturdays, Sundays, public holidays, and any day falling within the periods of 22 to 24 December, 27 to 31 December, and 2 to 10 January. Miscalculating this deadline by relying on calendar days can lead to a failure to issue the schedule in time, which typically results in full liability for the claimed amount.

Can a principal ignore my civil works invoice if they believe the work is defective?

No, holding a genuine belief that work is defective is legally insufficient to withhold funds without following the proper procedure. If the principal fails to issue a valid payment schedule detailing the exact deductions within the timeframe required by section 76, they may become liable for the full amount as a statutory debt — recoverable by the claimant after issuing a section 99 warning notice.

What is the section 78 debt recovery pathway for unpaid civil contractors?

If a respondent fails to provide a payment schedule or pay the owed amount, section 78 of the BIF Act provides a mechanism to pursue the unpaid money. After issuing a section 99 warning notice within 30 business days of the due date for payment, the civil contractor may bypass standard contractual claims and recover the unpaid amount as a statutory debt in a court of competent jurisdiction.


This guide is for informational purposes only and does not constitute legal advice. For advice tailored to your specific circumstances, please contact Merlo Law

 



Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
Urban Building

Contact Us

Contact us on 1300 110 253 to discuss your matter or complete our online form and we will contact you as soon as possible. 

Rectangle Dark (1).png
  • Instagram
  • Facebook
  • X
  • LinkedIn
  • YouTube

QLD SERVICES

Contract drafting and review

Commercial document preparation

Security of Payment (BIF Act)

Adjudication and payment claims

Dispute resolution and litigation

Mediation and arbitration

QBCC licensing and disputes

Project risk management

Tender process guidance

Defective work claims

WHS and environmental law

Employment and industrial relations

Insolvency and restructuring

Property development law

Professional negligence claims

Body Corporate legal advice

NSW SERVICES

Contract drafting and review

Commercial document preparation

Security of Payment (SOP Act)

Adjudication and payment claims

Dispute resolution and litigation

Mediation and arbitration

NSW Fair Trading licensing and disputes

Project risk management

Tender process guidance

Defective work claims (Home Building Act)

WHS (SafeWork) and environmental law

Employment and industrial relations

Insolvency and restructuring

Property development law

Professional negligence claims (DBP Act)

Strata and Community Title advice

NEW SOUTH WALES

02 8252 8752

info@merlolaw.com.au

Level 5, 115 Pitt Street

Sydney NSW 2000

OPEN HOURS

Mon - Fri

9am - 5pm

Sat - Sun     

By appointment only

Individual liability limited by a scheme approved under professional standards legislation.

© 2022 | M Salazar Services Pty Ltd ACN 652 059 071 trading as Merlo Law ABN 88 652 059 071, a law practice incorporated in Queensland, Australia | All Rights Reserved | Terms & Conditions | Privacy

bottom of page