top of page
Apartment Building

Publications

Can You Withhold A Subbie’s QLD Payment Claim If They Miss Payroll?

  • Writer: John Merlo
    John Merlo
  • Apr 15
  • 12 min read

Updated: May 8


Key Takeaways

  • A missed subcontractor payroll does not automatically invalidate their progress claim: You must still assess the claim under the strict provisions of the Building Industry Fairness (Security of Payment) Act 2017 (Qld).

  • The 15-business-day response window is critical: Failing to serve a compliant payment schedule outlining your proposed deductions typically converts the claimed amount into a statutory debt payable on the due date for the relevant progress payment, regardless of the subcontractor's default.

  • Set-off deductions require precise quantification: To successfully withhold funds for take-out costs or liquidated damages, the payment schedule must detail the exact contractual mechanism and calculated costs.

  • Direct payments to crews carry legal risk: Attempting to pay the subcontractor’s workforce directly without formal assignment documentation may expose the head contractor to double-payment claims if a liquidator is appointed.




The earthworks subcontractor’s leading hand has just walked into the site office to tell you the crew’s Friday pay didn’t hit their accounts, and the excavators have been shut off. Meanwhile, sitting on your desk is the subcontractor’s massive end-of-month progress claim for the subdivision's trenching works. You know they are in breach of their employment obligations and likely the subcontract, but under Queensland law, their internal financial crisis does not hit pause on your ticking payment response clock. If you freeze their progress payment to fund a take-out of the remaining works without executing the correct statutory paperwork, you risk transforming their breach into your immediate financial liability. The next 48 hours dictate whether you control the financial fallout or hand the defaulting subcontractor an undefended adjudication win.

 

 

The 48-Hour Decision Matrix: Securing the Site vs Validating the Payment Claim

The immediate priority is containing the operational damage on the ground without triggering a fatal procedural error on paper. The actions you take during this initial walk-off phase will establish the evidentiary foundation you need to lawfully withhold funds and execute your contractual rights.

 

Separating Statutory BIF Act Liability From Contractual Set-Off Rights

A subcontractor breaching their contract by missing payroll does not freeze the statutory timeline governing your response to their payment claim. You must distinctly separate your contractual right to set-off costs from your procedural obligations under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). Your commercial instincts might scream to lock the gates and refuse payment until the dust settles on the abandoned works. However, acting solely on the subcontract’s default provisions while ignoring the security of payment Queensland framework is a critical misstep.

 

Under Queensland's BIF Act, a subcontractor's suspected insolvency or breach of contract does not suspend the head contractor's strict statutory obligation to respond to a valid payment claim.

 

The head contractor must separately administer the BIF Act procedure—specifically the payment schedule—while simultaneously running the contractual procedure for notices of default. Relying on competent Queensland building and construction lawyers early in this sequence can often prevent a manageable site issue from becoming an unmanageable statutory debt.

 

Triaging the Subcontractor's Progress Payment Claim Validity Under Section 68

Is the document sitting on your desk legally capable of triggering the statutory countdown? The very first forensic check a Contracts Administrator must perform is validating the document under section 68 of the BIF Act to confirm it constitutes a legally compliant progress payment claim civil contractor Before assessing any deductions for the site walk-off, you must verify that the claim explicitly identifies the construction work completed, states the exact amount claimed, and includes a clear request for paymentIf the document fails to meet these threshold formal requirements — including any additional information prescribed by regulation under section 68(1)(d) — it does not enliven the BIF Act timeline. Identifying a jurisdictional flaw in the claim's validity is often the strongest initial step to buy crucial time to assess the commercial reality of the subcontractor's default.


Stop guessing whether that invoice is a valid BIF Act claim. Instruct our team to conduct an urgent statutory review before your 15-day response window evaporates.

 


Critical 48-Hour Site Security Interventions That Minimise Dispute Exposure

What immediate site actions best protect the head contractor's commercial and legal position? Securing the physical site and initiating formal contractual steps must happen concurrently with the BIF Act administrative review. The Queensland Building and Construction Commission (QBCC) actively monitors the financial stability of the state's commercial building sector, and formalising your response to a financially distressed subcontractor is critical to maintaining your own compliance profile with the primary Queensland regulator.

 

To minimise your exposure to a protracted subcontractor dispute civil contractor Queensland execute the following interventions within the first 48 hours:

 

  • Secure plant, equipment, and materials: Immediately lock down the site to prevent the removal of unfixed materials or essential plant that may be subject to contractual step-in rights or liens.

  • Review subcontract suspension clauses: Audit the specific terms of the subcontract to determine the exact notice period required before you can legally suspend their remaining scope of work.

  • Draft and serve a formal notice of default: Issue a written notice explicitly detailing the breach (e.g., failure to maintain progress, abandonment of works) without prematurely terminating the contract, which could invite a damaging repudiation claim.

  • Document the exact status of the works: Photograph and catalogue the precise state of open trenches, compaction levels, and incomplete tasks on the day the crew walked off to establish the baseline for future take-out cost calculations.

 

 

Drafting the Defending Payment Schedule to Enforce Contractual Deductions

Once the physical site is locked down and you have confirmed the claim on your desk is formally valid, the countdown shifts entirely to the payment schedule deadline. The document you draft right now determines whether you can legally withhold the cash required to fund the take-out, or whether you will become liable for the subcontractor's entire claim by default.

 

The 15-Business-Day Statutory Trap for Withholding Subcontractor Funds

Warning: The most dangerous assumption a head contractor can make when a subcontractor abandons the site is that the breach releases them from their BIF Act administrative obligations. If you intend to withhold funds from the pending Building Industry Fairness Act guide claim to cover the costs of completing the abandoned works, section 76 strictly controls your timeline. A party receiving a payment claim must provide a payment schedule within whichever period ends first — the period specified in the construction contract, or 15 business days after the payment claim is given to the respondent.

 

Failing to serve this document within the statutory window carries a maximum penalty of 100 penalty units, and notably, the obligation to serve a payment schedule does not arise at all if the respondent pays the full claimed amount on or before the due date for the relevant progress payment. Failing to serve this document within the statutory window is likely to strip the head contractor of their right to raise contractual set-offs or jurisdictional defences if the matter proceeds to adjudication.

 

A payment schedule under Queensland law is the mandatory written response to a payment claim that must state the amount proposed to be paid and the detailed reasons for withholding any portion of the claim.

 

Quantifying Liquidated Damages and Take-Out Costs for Adjudicator Scrutiny

Expert insight: Broad, unquantified allegations of "breach of contract" or "incomplete works" are routinely rejected during adjudication when a head contractor attempts to set off funds against a defaulting subcontractor. The payment schedule must detail the specific contractual mechanism permitting the deduction and provide a precise mathematical breakdown of the anticipated take-out costs, projected liquidated damages, or rectification expenses. Relying on the official Industry Guide to Security of Payment Laws provides baseline expectations, but adjudicators will scrutinise the evidentiary backing of every dollar you attempt to withhold.

 

The practical standard adjudicators apply is closer to a line-item cost estimate than a letter of complaint. For take-out costs on abandoned civil works, this means the schedule should include a scope-by-scope breakdown of the remaining work referenced against the contract's schedule of rates, a preliminary quote or internal rate card for the replacement contractor or direct labour, and a calculation of the daily rate and accruing period if liquidated damages are being claimed.

 

A payment schedule that simply states the subcontractor "abandoned the works leaving $X worth of incomplete trenching" will almost invariably be treated as an unquantified assertion rather than a valid set-off. Adjudicators in Queensland are not required to do the arithmetic for you — if the number is not in the schedule with a clear derivation, it typically will not survive challenge. Where the take-out has not yet been fully costed at the time the schedule must be served, the defensible approach is to state the best available estimate with transparent assumptions and reserve the right to update the figure, noting that any cost incurred beyond the scheduled amount cannot be introduced later.

 

Getting that preliminary cost estimate on paper — even a rough one from a trusted civil subcontractor — before the 15-business-day window closes is often the difference between a deduction that holds and one that is rejected in its entirety. Ensuring your schedule withstands this scrutiny is where experienced construction law advice often proves decisive.

 

At Merlo Law, our on-the-ground experience across Queensland and New South Wales means we know exactly how to architect a payment schedule that survives forensic adjudicator scrutiny. We work directly with your project teams to translate raw take-out costs into legally robust contractual set-offs that effectively protect your working capital. Secure your commercial position by instructing us to build a precise, evidence-backed defense that systematically dismantles a defaulting subcontractor's claim.


Why Section 74 Voids "Pay When Paid" Excuses for Withholding Progress Payments

When a subcontractor’s crew walks off site due to unpaid wages, it is a common misconception among head contractors that they can stall the progress payment by claiming they are still waiting on funds from the principal developer. This strategy is legally void. Under section 74 of the Building Industry Fairness (Security of Payment) Act 2017 any contractual clause that attempts to make a contractor's right to payment contingent on the higher party receiving payment is void and legally unenforceable. The enforceability of this clause depends entirely on the strict statutory prohibition, which actively severs the head contractor's cash flow problems from their liability to pay the subcontractor. Therefore, you cannot rely on upstream payment delays as a valid reason for withholding funds in your payment schedule.

 

Consequences of Issuing a Deficient Payment Schedule Under Section 77

What happens if you miss the deadline or serve a schedule that fails to explicitly state your reasons for withholding payment? The consequences under section 77 are severe and immediate. Failing to issue a payment schedule within the statutory timeframe renders the respondent strictly liable for the full claimed amount on the due date for the relevant progress payment, converting the disputed invoice into a statutory debt.

 

The consequence of losing the ability to raise contractual defences or set-offs in any subsequent adjudication proceeding flows from the broader adjudication provisions of the BIF Act, not from section 77 itself — however, the practical effect is the same: a missed payment schedule deadline substantially strips the head contractor of their ability to defend the claim in that rapid-resolution forum.

 

Executing a Take-Out of Remaining Civil Works Without Forfeiting Adjudication Rights

With the payment schedule correctly lodged and the immediate cash bleed contained, your focus inevitably shifts back to finishing the project. However, stepping in to complete the defaulting subcontractor's open trenching or compaction works is fraught with legal and evidentiary traps. If the disentanglement is mishandled physically or financially, it can cripple your defensive position when the dispute inevitably escalates.

 

Procedural Traps When Directly Paying the Subcontractor's Civil Works Crew

Expert insight: A frequent tactical error occurs when a head contractor, desperate to keep the project moving, verbally agrees to pay the defaulting subcontractor's crew directly to finish the shift. The commercial logic is understandable — the workers are on site, the plant is warm, and a day's productivity is salvageable. The legal exposure, however, is substantial and routinely underestimated.

 

The core problem is that the payments go to individuals who have no contractual relationship with the head contractor. The subcontracting entity — the company — remains the counterparty to the subcontract, and its right to be paid under that subcontract does not extinguish because its own employees received wages from a third party.

 

When a liquidator is subsequently appointed, which is a foreseeable outcome where a subcontractor has already missed a payroll run, the liquidator's obligation is to recover assets for creditors — and the outstanding subcontract progress claim is one of those assets. The liquidator is not bound by any informal understanding reached between the head contractor and the workers on the day, and courts have consistently upheld the liquidator's right to pursue the full contract amount regardless of what the head contractor paid downstream.

 

The head contractor then faces a situation where they have paid the workers informally and are simultaneously liable to the liquidator for the original contract sum. The only mechanism that severs this exposure is a formally executed deed of novation or assignment that transfers the subcontractor's contractual rights and obligations to the new contracting arrangement before any direct payments are made — not after, and not on a handshake. If the subcontractor's principals are uncontactable or unwilling to execute that documentation, the safer course is to engage a replacement subcontractor under a fresh contract and issue a nil payment schedule against the original claim, preserving the set-off position rather than attempting an informal crew-level rescue.


Don't risk paying for the same civil works twice. Request an urgent review of your step-in rights and assignment deeds before you release a single dollar to an abandoned crew.


Evidentiary Requirements for Valuing Incomplete Trenching and Compaction Works

When you assume control of the abandoned site, the documentation you gather forms the core evidence supporting the deductions claimed in your payment schedule. You must implement rigorous tracking to substantiate the cost of the take-out. This typically involves commissioning independent dilapidation reports, maintaining dated photography of the open trenches, and establishing separate cost codes for the replacement contractors or internal labour used to finish the scope. Furthermore, head contractors must be aware of how the recent expansion of the Queensland  Project Trust Account (PTA) framework interacts with retained funds and how those funds are legally accessed to cover the completion costs.

 

Successfully defending a deduction for incomplete civil works at adjudication requires contemporaneous site evidence, such as dated compaction test failures and independent superintendent reports, gathered immediately upon the subcontractor's departure.

 

Defending Against a Section 78 Adjudication Application Following a Hostile Take-Out

Even with a perfectly drafted payment schedule detailing the take-out costs, the withholding of funds is likely to trigger an escalation. Under section 78, where a respondent fails to pay the owed amount, the claimant possesses a statutory right to either sue for the debt in court or commence adjudication. Critically, section 78(3) and (4) also entitle the claimant to serve written notice of their intention to suspend construction work under section 98 of the Act, provided that notice expressly states it is made under the Act. 


For a head contractor already managing an abandoned civil site, a formal suspension notice from the subcontractor compounds the legal complexity and must be treated as a live risk when assessing the consequences of a deficient or absent payment schedule. If the subcontractor proceeds with an adjudication application Queensland, the head contractor’s defence is strictly limited to the reasons explicitly detailed in the payment schedule. Any newly discovered defects, unquantified delays, or additional take-out costs identified after the schedule was served cannot be introduced, which may leave the head contractor exposed to an adverse determination.

 

 

Conclusion

When the excavators are turned off and the subcontractor's crew is demanding their Friday wages, the pressure to make an immediate, commercially pragmatic decision is immense. However, as this guide demonstrates, prioritising site momentum over strict statutory compliance is the fastest way to assume the defaulting subcontractor's financial liabilities. Your right to withhold funds to cover the take-out of the abandoned trenching and compaction works is not automatic—it is entirely contingent on adhering to the unforgiving 15-business-day response window mandated by the BIF Act.

 

The commercial reality of a failed civil subcontract requires dual processing: securing the physical site to quantify the incomplete works, while simultaneously executing the administrative response required to validate those deductions. Failing to issue a compliant payment schedule with a mathematically precise breakdown of your set-off costs strips away your defensive rights and converts the disputed claim into an enforceable statutory debt.

 

If you are currently holding a progress claim from a distressed subcontractor and the timeline is running, do not attempt to navigate the set-off process using generic breach notices. Immediately catalogue the site evidence and draft a payment schedule that explicitly links your anticipated completion costs to the relevant contractual mechanisms before the statutory window closes.

 


FAQs

What makes a progress payment claim valid under the BIF Act?

A valid payment claim must clearly identify the construction work carried out, state the exact amount the subcontractor believes they are owed, and include a request for payment. If the document fails to meet these threshold requirements, it may not trigger the strict statutory response timelines under Queensland law. Identifying these formal deficiencies is an essential first step in determining your response strategy.

What happens if I miss the 15-business-day deadline to serve a payment schedule?

Failing to serve a compliant payment schedule within 15 business days (or sooner if the contract dictates) generally renders the head contractor strictly liable for the full amount claimed. This oversight prevents you from relying on contractual set-offs, such as liquidated damages or take-out costs, and effectively bars you from defending the claim if the subcontractor proceeds to adjudication.

Can I withhold a subcontractor's payment because the developer hasn't paid me yet?

No. Under Queensland law, any contractual clause attempting to make a subcontractor's payment contingent on the head contractor receiving funds from the principal is void. The BIF Act strictly prohibits these "pay when paid" arrangements, meaning upstream cash flow issues cannot be used as a valid reason to withhold funds in a payment schedule.

How much detail do I need to include in a payment schedule if the subcontractor walks off site?

You must provide a precise mathematical breakdown of the proposed deductions, rather than relying on broad statements like "incomplete works" or "breach of contract." To successfully withhold funds for a take-out, the schedule should explicitly detail the projected completion costs, the relevant contractual clauses permitting the deduction, and any related liquidated damages.

Is it legally safe to pay the defaulting subcontractor's crew directly to finish the job?

Paying a subcontractor's crew directly without formalizing the arrangement through a deed of assignment or issuing a nil payment schedule creates significant financial risk. If the subcontractor enters insolvency, the appointed liquidator may pursue the head contractor for the original subcontracted amount, which can result in the head contractor paying for the same labour twice.

Can I raise new reasons for withholding payment during adjudication if I didn't include them in the payment schedule?

No. If the dispute escalates to an adjudication application, the head contractor is strictly limited to the reasons already detailed in their original payment schedule. Any defects or take-out costs discovered after the schedule was served typically cannot be introduced as new evidence, potentially weakening your defensive position.


This guide is for informational purposes only and does not constitute legal advice. For advice tailored to your specific circumstances, please contact Merlo Law


Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
Urban Building

Contact Us

Contact us on 1300 110 253 to discuss your matter or complete our online form and we will contact you as soon as possible. 

Rectangle Dark (1).png
  • Instagram
  • Facebook
  • X
  • LinkedIn
  • YouTube

QLD SERVICES

Contract drafting and review

Commercial document preparation

Security of Payment (BIF Act)

Adjudication and payment claims

Dispute resolution and litigation

Mediation and arbitration

QBCC licensing and disputes

Project risk management

Tender process guidance

Defective work claims

WHS and environmental law

Employment and industrial relations

Insolvency and restructuring

Property development law

Professional negligence claims

Body Corporate legal advice

NSW SERVICES

Contract drafting and review

Commercial document preparation

Security of Payment (SOP Act)

Adjudication and payment claims

Dispute resolution and litigation

Mediation and arbitration

NSW Fair Trading licensing and disputes

Project risk management

Tender process guidance

Defective work claims (Home Building Act)

WHS (SafeWork) and environmental law

Employment and industrial relations

Insolvency and restructuring

Property development law

Professional negligence claims (DBP Act)

Strata and Community Title advice

NEW SOUTH WALES

02 8252 8752

info@merlolaw.com.au

Level 5, 115 Pitt Street

Sydney NSW 2000

OPEN HOURS

Mon - Fri

9am - 5pm

Sat - Sun     

By appointment only

Individual liability limited by a scheme approved under professional standards legislation.

© 2022 | M Salazar Services Pty Ltd ACN 652 059 071 trading as Merlo Law ABN 88 652 059 071, a law practice incorporated in Queensland, Australia | All Rights Reserved | Terms & Conditions | Privacy

bottom of page