top of page
Apartment Building

Publications

Security of Payment: Can You Stay a BIF Act Judgment if a Subcontractor is Insolvent?

  • Writer: John Merlo
    John Merlo
  • 17 hours ago
  • 15 min read

Key Takeaways

  • When a builder moves to set aside a judgment under the Building Industry Fairness (Security of Payment) Act 2017 (Qld) ("BIF Act"), section 93(4) of the BIF Act bars them from bringing a counterclaim, raising a defence about matters under the construction contract, or challenging the adjudicator's decision.

  • The Queensland Supreme Court may nonetheless stay enforcement of the judgment where paying it poses a risk of irrecoverable loss due to the subcontractor's precarious financial position, with rule 800 of the UCPR being one expression of that power.

  • The disputed money is held in court rather than left with the builder: section 93(4)(b) of the BIF Act requires payment into court as security when a respondent seeks to set aside the judgment, and the court expects the same before granting a stay.

  • Mere suspicion of a subcontractor's cash flow issues is typically insufficient; builders must present cogent financial evidence, such as unsatisfied statutory demands or active winding-up applications. The threshold is a real and serious risk of non-recovery, not certainty of insolvency.

You have just opened an adjudicator's decision ordering you to pay a subcontractor a substantial sum, but the reality on site tells a different story: their work is riddled with defects, and word on the supply chain is that the company is about to go under. If you hand over the cash now to comply with the statutory "pay now, argue later" regime, you face a very real danger that those funds will vanish into a liquidator's trust account before you can ever formally assess or recover your defect back-charges. The immediate priority is not just disputing the quality of the work, but finding a way to freeze the mandated payment. The short answer is yes—you can freeze the payment, but only on strict conditions and only if you move fast. This article walks you through the exact mechanism under Queensland law to stay enforcement, intercept the cash, and hold it safely in court before it is lost to corporate collapse.

 

 

The Tactical Window Between Adjudication Loss and Subcontractor Collapse

You are currently staring down a rapidly closing timeline between the adjudicator handing down their decision and the subcontractor moving to freeze your bank accounts or enforce the debt. You are likely frustrated by a system that seems to prioritise a failing trade's cash flow over your legitimate defect claims. This section outlines the immediate timeline you face and the distinct procedural mechanisms available to intercept the flow of cash before the subcontractor executes on the judgment.

 

Assessing the Risk of an Unrecoverable Adjudication Judgment

When a financially distressed subcontractor succeeds in an adjudication in Queensland and files the resulting certificate as a judgment debt, the builder faces severe commercial peril. The core danger is simple: once you pay, the money may be gone for good. If the subcontractor enters liquidation before your defect claims are resolved, the sum you handed over becomes almost impossible to recover.

 

Once the funds are paid over, they are rapidly absorbed into the subcontractor's general accounts. If the subcontractor then collapses under the insolvency regimes of the Corporations Act 2001 (Cth) ("Corporations Act")—the primary federal corporate legislation governing company failures—the builder typically becomes just another unsecured creditor. Any future victory in a tribunal may prove hollow: a judgment against a hollowed-out company is worth little. The solvent builder is left to absorb the full cost of rectification alone.

 

Security of Payment Rules: Why Your Defect Claim Can't Cancel the Judgment—But Can Still Freeze It

To navigate this crisis, you need to separate two very different things: the strict enforcement mechanisms of the payment legislation, and the broader procedural protections available in the courts. Section 93 of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) directly governs the filing of adjudication certificates as judgment debts. When a respondent commences proceedings to set aside a judgment based on an adjudication certificate under this Act, section 93(4) statutorily bars them from bringing any counterclaim, raising any defence in relation to matters arising under the construction contract, or challenging the adjudicator's decision. The BIF Act explicitly prohibits using the underlying defect dispute to attack the judgment debt itself. Critically, section 93(4)(b) also requires the respondent, in those set-aside proceedings, to pay the unpaid portion of the adjudicated amount into court as security pending the final decision—so the obligation to pay the disputed money into court arises from the statute itself, not merely from the court's discretion. Critically, section 93(4)(b) also requires the respondent, in those set-aside proceedings, to pay the unpaid portion of the adjudicated amount into court as security pending the final decision—so the obligation to pay the disputed money into court arises from the statute itself, not merely from the court's discretion.

 

However, a distinct procedural pathway exists outside the substantive dispute. The court retains a discretionary power to stay the enforcement of a money order, one expression of which is rule 800 of the Uniform Civil Procedure Rules 1999 (Qld) ("UCPR"), the rule dealing with stays of enforcement. While you cannot use your defect claims to set aside the BIF Act judgment, you can ask the court to stay the enforcement of that judgment debt on the grounds that enforcing it would cause severe and irreparable prejudice due to the subcontractor's precarious financial position. This is a demanding jurisdiction: the court weighs the balance of convenience, and the money in dispute will ordinarily remain paid into court while the substantive contractual dispute is resolved.

 

Executing Immediate Triage Post-Decision

In practice, the five business days rarely gives you the runway it appears to.  Following an adverse adjudication decision, a builder typically has only five business days to pay the adjudicated amount under section 90 of the BIF Act (or such later date as the adjudicator decides). If payment is not made, the subcontractor can request that the registrar issue an adjudication certificate under s91 of the BIF Act and then file that certificate in court as a judgment debt under s93(1). From that moment, the builder is highly exposed. Enforcement mechanisms, such as garnishee orders redirecting funds directly from the builder's bank accounts, can often be secured rapidly and without prior warning. Subcontractor lawyers who deal in security of payment work will often have the request for an adjudication certificate drafted before the decision even lands, and they file the moment the clock expires. Treat the decision date, not the payment due date, as the trigger for mobilising.

 

The other reality is that enforcement moves faster than most builders expect. Once the certificate is filed as a judgment, an enforcement warrant or garnishee can issue on an ex parte basis, meaning the first you may hear of it is your bank freezing the account. Build the stay application in parallel with any request for reasons or internal review — do not run those steps sequentially, or the funds may be gone before you file.

 

Consequently, you must prepare and file your stay application within days, not weeks, of the adjudication decision being released. Delay while trying to interpret your obligations under a general BIF Act guide, and you may find the funds already seized under enforcement warrants—rendering the protection of a stay moot.

 

 

Evidentiary Thresholds for Proving the Subcontractor's Insolvency Risk

Proving what everyone on site already knows—that the subcontractor is out of cash and teetering on the edge of collapse—is harder than it sounds. However, securing a stay of enforcement is an uphill battle, as courts are highly reluctant to disrupt the BIF Act's objective of facilitating cash flow in the industry. To convince a judge to freeze the judgment debt, you must pivot from site rumours and suspicions to admissible, compelling evidence of the subcontractor's imminent failure. This section examines exactly what proof the Supreme Court requires to find that a subcontractor is in a precarious financial position.

 

Why Site Rumours Fail the "Precarious Financial Position" Test

The Supreme Court typically requires clear, documented evidence of financial distress, rather than mere suspicion, before it may consider a subcontractor to be in a precarious financial position for the purposes of a stay. Importantly, the threshold is not certainty of insolvency. In Taringa Property Group Pty Ltd v Kenik Pty Ltd [2024] QSC 327, Hindman J expressly rejected the argument that the risk of non-recovery must reach the level of certainty, and confirmed that the party to be paid need not be shown to be in external administration or "positively proved to be hopelessly or otherwise insolvent". What is required is cogent evidence of a real, and in cases such as this a high, risk of irrecoverable loss.

 

Warning: Relying on anecdotal evidence of unpaid suppliers, slow progress on site, or industry gossip is typically insufficient to secure a stay of enforcement. If an application lacks hard financial data, a court is likely to view it as a tactical attempt to subvert the statutory "pay now, argue later" intent. Consequently, bringing an under-evidenced application can result in the stay being dismissed, which may expose the builder to adverse costs orders while still leaving them vulnerable to a subcontractor insolvency builder scenario.

 

Gathering Cogent Financial Evidence for the Supreme Court

Expert insight: To successfully argue for a stay, builders should not wait until the decision drops to start assembling evidence — the sourcing needs to begin the moment insolvency is suspected. A current ASIC company extract and, where available, a company charge search will show recent defaults, changes in directorship, or fresh security interests that signal a trade under pressure. These are cheap, fast, and carry more weight with a judge than any amount of site commentary. Beyond the register, monitor the published winding-up application lists and any Federal Court or Supreme Court filings naming the subcontractor.

 

Evidence of an active winding-up application, an unsatisfied statutory demand, or a prior unpaid judgment is the kind of objective, documented material courts treat as cogent. The most underused source is other creditors. If suppliers or other subbies on the same project are also unpaid, a short affidavit from one of them confirming dishonoured payments or bounced arrangements can be decisive — it converts "site rumour" into sworn evidence. In urgent scenarios, engaging an alternative dispute resolution Queensland practitioner early can help structure this evidence before enforcement strikes.

 

The Impact of the Taringa Property Group Precedent

Once you have assembled that cogent evidence, the next question is how a court actually weighs it. The leading Queensland authority is Taringa Property Group Pty Ltd v Kenik Pty Ltd [2024] QSC 327. There, a principal (Taringa) had been ordered to pay its head contractor (Kenik) an adjudicated amount of approximately $4.2 million, and Kenik had obtained judgment for the debt. Taringa applied both to set aside the adjudication for jurisdictional error and, in the alternative, to stay enforcement of the judgment, on the basis that Kenik was in a precarious financial position and unlikely to be able to repay the money if Taringa later succeeded on its substantive contract claims. Hindman J dismissed the challenge to the adjudication itself but granted the stay, marking the first time a Queensland court had stayed enforcement of a BIF Act judgment where the party to be paid was not already in liquidation or external administration.

 

The decision is important for the principle rather than the precise parties: while Taringa concerned a principal and a head contractor, the same reasoning applies to a builder facing payment to a subcontractor in financial distress. Justice Hindman emphasised that considerable caution attends the grant of a stay because it detracts from the BIF Act's "pay now, argue later" purpose, and that in the ordinary case stays will not be granted. The court balanced that strong statutory policy against the very high risk that the adjudicated sum would be irrecoverable if paid out to a company on the brink of collapse. Notably, Taringa was required to pay the adjudicated amount (with interest and costs) into court, and the funds were preserved there pending resolution of the substantive dispute.

 

The aftermath is a caution as much as a comfort. Kenik was subsequently wound up in insolvency (see Barrett Group Pty Ltd v Kenik Pty Ltd [2025] QSC 25, where Kenik accepted it was insolvent and had not traded since August 2023), vindicating the concern that justified the stay. However, in the later decision Taringa Property Group Pty Ltd v Kenik Pty Ltd (in liq) [2025] QSC 222, the court refused Taringa leave under s471B of the Corporations Act to continue its proceeding against the company outside liquidation, holding that its monetary claims should be dealt with through the liquidator's proof of debt process notwithstanding the funds held in court. Because Taringa was under appeal at the time of writing and the surrounding case law continues to develop, its precise scope should be confirmed with current advice before relying on it.

 

 

Paying the Adjudicated Amount Into Court to Neutralise Enforcement

You may be resistant to the idea of parting with the cash—especially when you believe the subcontractor owes you money for rectifying their defective work—but attempting to hold onto the funds entirely while seeking a stay is rarely a viable strategy. To prove to the Supreme Court that your application is rooted in a genuine concern for asset preservation, you will typically need to pay the adjudicated amount into the court's trust. This section explains why this financial trade-off is often the only pathway to successfully ring-fencing the judgment debt and protecting your bottom line.

 

Why the Court Requires Payment as a Condition of the Stay

Payment of the adjudicated amount into court is central to protecting yourself. Under section 93(4)(b) of the BIF Act, a respondent who commences proceedings to set aside the judgment is already required to pay the unpaid portion into court as security; and where a stay of enforcement is sought, the court will in any event expect the disputed funds to be held in court rather than left with the builder.

 

The rationale behind this requirement is a deliberate judicial balancing act. The court's objective is to protect the builder from an irrecoverable loss to a liquidator while simultaneously ensuring the builder isn't merely using the stay mechanism to disguise their own cash flow issues or circumvent the statutory mandates of security of payment Queensland. By holding the funds in the court registry, a judge can neutralise the immediate enforcement threat—enforcement being a court process under the UCPR, not one administered by the QBCC, whose Adjudication Registry deals only with the earlier adjudication application and appointment stage—without undermining the overarching legislative intent that disputed funds should not simply remain in the principal's pocket.

 

Strategic Advantages of Ring-Fencing the Judgment Debt

Expert insight: Once the funds are securely ring-fenced in the court's registry, the commercial dynamics of the dispute shift entirely — and the shift is most obvious the moment a liquidator or administrator is appointed. An insolvency practitioner running a distressed estate wants certainty and a quick, clean realisation of assets; a contested pool of money sitting in a court trust, subject to your quantified defect claim, is neither. That friction is your leverage. A liquidator weighing the cost of litigating your defect claim against a modest, prompt commercial resolution will frequently take the resolution, particularly where the estate has limited funds to run the fight.

 

Contrast that with the alternative. Had the money reached the subcontractor's general accounts before collapse, you would be lodging a proof of debt and waiting in line with every other unsecured creditor for cents in the dollar—if anything at all.

 

 The practical tactic is to have your defect claim quantified and evidenced before the appointment, not after. Walking into negotiations with a substantiated back-charge figure that already exceeds or approaches the ring-fenced sum tells the liquidator exactly why fighting you is uncommercial. This creates a distinct strategic advantage when navigating building and construction disputes, as the protected pool of funds provides concrete leverage during settlement negotiations that would otherwise be absent if the money had vanished into the subcontractor's general accounts.

 

 

Securing Defect Back-Charges While the UCPR Stay Operates

Securing a stay of enforcement provides immense relief, but it is merely a holding pattern; it freezes the funds in court, but it does not resolve your underlying problem. To eventually recover that money and offset it against the costs you are incurring to fix the site, you must aggressively pursue your substantive contractual claims against the subcontractor. This section covers the transition from obtaining the temporary protection of a stay to executing your final recovery strategy for defective or incomplete work.

 

Commencing Concurrent Proceedings for Contractual Breaches

A stay of enforcement under the UCPR is a temporary protective measure, requiring the builder to actively pursue concurrent legal proceedings to finally determine the underlying contractual defect claims.

 

Freezing the funds does not automatically result in those funds being returned to you. The court's willingness to maintain the stay is entirely contingent on the builder promptly pursuing a final determination of the contractual dispute. This means you must formally commence substantive court proceedings or file an application with the Queensland Civil and Administrative Tribunal (QCAT)—the tribunal handling underlying contractual defect disputes—to quantify and prove your defect rectification costs. Filing these substantive proceedings validates the necessity of the stay by demonstrating to the Supreme Court that a genuine, quantifiable claim exists to offset against the ring-fenced funds.

 

Scenario: Offsetting Ring-Fenced Funds Against Rectification Costs

Consider a scenario where a builder is ordered at adjudication to pay $150,000 for a progress claim, but they successfully secure a stay by paying that amount into court, citing the subcontractor's impending insolvency. Concurrently, the builder formally prosecutes a back charge subcontractor builder claim for $180,000 in severe waterproofing and structural defects left by that same trade. When the subcontractor subsequently enters liquidation, the builder litigates the defect claim to a final determination. Because the $150,000 is held in trust by the court, rather than lost to the liquidator's general pool, the court can manage the set-off process. This mechanism may allow the builder to recover the ring-fenced $150,000 to cover the bulk of their rectification liabilities, turning a potential total loss into a managed, offset outcome. This outcome is not automatic,

 

however. Once the subcontractor is in liquidation, the builder's monetary claims may need to be pursued through the liquidator's proof of debt process rather than by continued litigation, and any set-off is subject to the mutual set-off rules in s553C of the Corporations Act and to the court's directions about the funds held. In Taringa Property Group Pty Ltd v Kenik Pty Ltd (in liq) [2025] QSC 222, for example, the court declined to let the paying party continue its claim outside the winding up, notwithstanding that the disputed funds were held in court. Ring-fencing the money is a powerful protection, but how it is ultimately applied will depend on the insolvency framework and the specific orders obtained.

 

 

Conclusion

When you are staring down an adjudicator’s decision ordering you to pay a subcontractor who has left defective work on site and is teetering on the edge of insolvency, the situation can feel hopelessly stacked against you. But the law does not abandon you to an irrecoverable loss. While the BIF Act bars you from using your defect claims to set aside the judgment, the Uniform Civil Procedure Rules provide a critical release valve.

 

By having the adjudicated amount held in the Supreme Court’s trust—whether as the security required under section 93(4)(b) or as the practical price of a stay of enforcement—you can effectively ring-fence those funds. This strategic move protects the cash from disappearing into a liquidator's hands while you actively prosecute your defect back-charges in concurrent proceedings, though how the ring-fenced money is ultimately applied will depend on the insolvency framework if the subcontractor is wound up.

 

Do not wait for the subcontractor to file the judgment debt and freeze your accounts. The window is measured in days. If you suspect a trade is going under, act now: compile objective documentary evidence of their financial distress—such as unanswered statutory demands or ASIC winding-up notices—and instruct an independent construction lawyer to draft an urgent stay application for the Supreme Court.

 

If an adjudication decision has just landed and you are worried about where the money will end up, contact our construction disputes team today for an urgent, confidential assessment—before enforcement strikes.



FAQs

Can I refuse to pay a BIF Act adjudication judgment if the subcontractor's work is defective in Queensland?

No, the BIF Act generally requires a respondent to pay the adjudicated amount regardless of underlying contractual defect claims. If you fail to pay, the subcontractor can file the adjudication certificate as a judgment debt to initiate enforcement action. However, a builder may apply to the Supreme Court for a stay of enforcement if paying the judgment poses a risk of irrecoverable loss due to the subcontractor's impending insolvency.

A stay of enforcement under Rule 800 of the Uniform Civil Procedure Rules 1999 (Qld) is a discretionary court order that can halt the collection of a judgment debt. In the context of building disputes, it can prevent a financially distressed subcontractor from enforcing an adjudication outcome while underlying defect claims are determined. The Supreme Court typically requires the builder to pay the disputed amount into court to secure this protective stay.

No, filing a counterclaim does not set aside the judgment debt. When a respondent moves to set aside a judgment based on an adjudication certificate, section 93(4) of the BIF Act bars them from bringing a counterclaim, raising a defence about matters arising under the construction contract, or challenging the adjudicator's decision. Builders must typically pursue their defect claims in separate proceedings while relying on a stay to temporarily freeze enforcement of the payment.

The Supreme Court may require cogent, documented financial evidence rather than mere site rumours to establish that a subcontractor is in a precarious financial position. This evidence often includes active winding-up applications, unsatisfied statutory demands, or clear financial disclosures showing the entity is under real financial pressure. The applicant need not prove the subcontractor is certainly insolvent, but without objective evidence of a genuine and serious risk of non-recovery, a judge is unlikely to grant an urgent stay of enforcement.

Paying the funds into court is required by section 93(4)(b) of the BIF Act when a respondent moves to set aside the judgment, and it is in any event expected by the court before a stay of enforcement will be granted, so as to demonstrate that the application is not merely a tactic to delay a payment the builder cannot afford. This mechanism balances the BIF Act's cash flow objectives with the builder's need to protect the funds from an impending liquidation. Once paid into the court's trust, the money is safely ring-fenced until the substantive defect dispute is resolved.

If the subcontractor enters liquidation, the funds held in the court's registry remain preserved from the general pool of unsecured creditors. Once a builder successfully quantifies and proves their defect back-charges in a concurrent tribunal or court proceeding, the court may allow the builder to offset those rectification costs against the ring-fenced funds. This procedure can help prevent the builder from suffering a total loss on the defect rectification work.


This guide is for informational purposes only and does not constitute legal advice. For advice tailored to your specific circumstances, please contact Merlo Law


Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
Urban Building

Contact Us

Contact us on 1300 110 253 to discuss your matter or complete our online form and we will contact you as soon as possible. 

bottom of page